First uploaded
Last updated 16 June 2010
|
|
Our
overall plan Development on the railway is divided into
phases. It was originally intended
that the phases would run sequentially as the railway expanded linearly. Experience has shown that in the funding
world, things can go seriously out of sequence. Some things have taken a back seat, whilst
others have come to the fore.
Nevertheless the phases still reflect the original geography, and the
‘UndergrounD’ map, in the style of the famous Harry Beck, will show how the
railway’s ambitious plans are divided into six phases. Phase 1 is any development between Whistle Inn
Halt south to Blaenavon (High Level) station.
We’ve run regular trains between Whistle Inn Halt and our main centre
at Furnace Sidngs since 1983, and since May 2010 down to Blaenavon (High
Level) station. Phases 2,3 and 6 are
further extensions southwards as far as the northern edge of Now, whilst we are quite happy to dabble in the
slippery political world, we are probably more at home galumphing around
where things are a little more tangible.
Nuts’n’bolts, rails, sleepers, concrete, timber – that’s our kind of
thing. That’s not to say that we are
not continually ferretting around in the background energetically seeking out
opportunities, but there’s unlikely to be anything for the passenger to see. What there is to see at the moment is all wrapped
up in Phase 1 – and Phase 1 is big and complex. For this reason Phase 1 is divided up into
a series of ‘steps’, as, ultimately, will all the other phases. The steps are sub-divided into sub-steps,
and sub-sub-steps, and so on. It’s all
become a bit of a joke at the PBR, but it is essential if all the jobs and
tasks that form a major project are not only to be managed physically, but
control is maintained over that vital resource – cash! |
|
PHASE 1 STEPS 1.0 Transport and Works Act
Order 1.1 Water and sewerage 1.2 Extension to Blaenavon
(high Level) 1.2.1 Trackwork 1.2.1.1 Trackwork – Furnace Sidings
to Forgeside 1.2.1.2 Trackwork – Forgeside to
Blaenavon (High Level) 1.2.2 Fencing 1.2.3 Platform at Blaenavon (High Level) 5 1.2.4 Bridges 1.2.4.1 1.2.4.2 New 1.2.4.3 1.2.4.4 1.2.4.5 1.2.4.6 1.2.5 Ecological assessment along the route 1.2.6 Rail over rail Bridge (Bridge 12) 1.2.6.1 Repair of Bridge 12 to
permit trains UNDER 1.2.6.2.Repair of Bridge 12 to
permit trains OVER 1.3 Infrastructure
improvements at Furnace Sidings 1.3.1 Construction of second platform at Furnace
Sidings 1.3.2
Erection of footbridge between platforms 1 and 2 at Furnace Sidings 1.3.3
Construction of a comprehensive station building on platform . 1.3.4
Provision of extra utilities, such as three phase electricity, and
broadband enabled telephone lines 1.3.5
Detailed improvements, such as fencing, crossing keepers hut and other
minor works 1.4 Infrastructure
improvements at Blaenavon (High Level) 1.4.1 - Construction of suitable buildings 1.4.2 - Construction of a run-round loop 1.4.3 – Construction of a second platform 1.4.4 - Erection of a footbridge at Blaenavon (High
Level) station. 1.5 Branch line to Big Pit
and Visitor Centre Step 1.5.1 - Rolling stock shed(s) with integrated visitor
facilities Step 1.5.2 – Branch line to Big Pit - track laying
and modifications to existing trackwork Step 1.5.3 – Construction of simple station near
Big Pit Step 1.5.4 – Acquisition and adaptation of suitable
passenger carrying vehicles Step 1.5.5 – Provision of suitable motive power Step
1.5.1 - Visitor centre
Step
1.5.2 - Trackwork
Step
1.5.3 - Station
Step
1.5.4 - Train
Step
1.5.5 - Engine
Step
1.5.6 - Safe walking route for
visitors over Br 12
Step
1.5.7 - Improvements to Old Pit road under Br 13 to connect to cycleway NCN46
Step
1.5.8 -Train shed
1.6 Extension to Top Shed 1.7 Fencing around Down
Exchange Sidings |
The panel alongside shows all the current steps in
their correct hierarchy, whilst each step is described in a little detail. However for a fuller account complete with
photos click HERE Step
1.0 - Transport & Works Act Order, and provision of water and sewerage
facilities to the site. Work started on the TWAO in December 2004 and was
completed in June 2006. Step 1.1 Water and
Sewerage This step number was
originally reserved for a step which planned to extend the railway only a
fraction of the way to Blaenavon (High Level), but it was abandoned in the
light of funding difficulties. It is
quite useful, now, to reserve this step number for the water and sewerage
facilities. Plans for the water were
worked up in December 2005, and water finally squirted onto site in May
2007. The second-hand loos arrived on
site in Spring of 2005, and the complete system commissioned by the Spring of
2007, though it was several months later before the trenches were filled. Step 1.2 - Furnace
Sidings to Blaenavon (High Level) The extension to Blaenavon
(High Level) was effectively completed on It is stressed that this
minimal extension, in itself, will not permit the operation of steam
locomotives, nor indeed, the use of loco-hauled stock, unless the special
(and wholly unprofitable) operation of
‘top and tailing’ is employed. This
technique would require two locomotives.
Only when a run round loop it Blaenavon High Level is complete will
conventional loco-hauled operation be possible. However we have a cunning plan to use our
recently acquired (but privately owned) EMUs and a Class 73 to provide loco
hauled trains over the route by means of ‘through control’. This plan permits no easy
access to Big Pit. There were plans in
the abandoned Step 1.1 to include a interchange halt on the route to
Blaenavon, but it would have permitted only modest interchange facilities
that would have been somewhat limited, difficult for mobility-impaired
passengers, and several hundred metres distant from of Big Pit . Sub-steps however 1.5.2 to 1.5.5 will
provide for comprehensive interchange facilities Step 1.3 - ‘Infrastructure improvements at Furnace
Sidings’ This step is intended to
provide a second platform, a footbridge and a long-awaited and comprehensive
station at Furnace Sidings to replace the completely unsuitable box van,
which despite a recent face lift and internal refit is really inadequate for
its intended purpose. The computer
generated image below, viewed from the west and looking east, gives an
impression of what the ensemble might look like when completed. The sub-steps are described below. |

Impression of second platform,
footbridge and station building at Furnace Sidings
Step 1.3.1 Construction of second platform at Furnace
Sidings
This work is complete. It consists of a massive front wall on
equally massive – and deep - foundations.
Its cosmetic brick front leaf was completed on
Step 1.3.2 Erection of footbridge between platforms 1
and 2 at Furnace Sidings
This work means the
dismantling, repair of components, re-assembly, and finally erection of the
bridge on the platforms at Furnace Sidings.
The original very battered and corroded, but genuine LNWR footbridge was
recovered from Hinckley station in Leicestershire. Fortunately the bridge divides neatly into
two supporting towers, two flights of steps and the main deck. Both towers are now in place, and welding and
other steel work on the main deck is now complete. It is now painted ready to be dropped into
place, but the wooden steps and decking remain outstanding. Tower 1 is bolted down with the flight walls
in place, whilst No.2 tower will be inched to its final resting place when the
main deck is dropped into place. At this
stage the stair flight will be attached.
It is planned that the main deck will be dropped into place during
Summer 2010.
Step 1.3.3 Construction of a comprehensive station
building on platform 1 with electricity, water and sewerage utilities.
The cost of the station
building is estimated at around £80,000, and even this assumes that much of the
building is constructed using volunteer labour.
The building has been planned in considerable detail, and could start
tomorrow if labour was available.
Although we have some statutory funding, we will nevertheless need to
make a substantial match to any statutory funding we receive.
Step 1.3.4 Provision of extra utilities, such as three
phase electricity, and broadband enabled telephone lines
Western Power Distribution
have been asked to provide estimates for various supply options, and a route
for the cable has now been decided. As
of June 2010 we have made no decision with regard to telephone lines.
Step 1.3.5 Detailed improvements, such as fencing,
crossing keepers hut and other minor works
The installation of a extra
fencing around the crossing and on the platform ramps is now complete, but no
work has started on the crossing keepers hut.
This must wait until there is a lull in the ‘heavyweight’ development.
Step 1.4 – Infrastructure improvements at Blaenavon
(High Level)
This step, identifies the
steps necessary to advance Blaenavon (High Level) station from its position as
‘statutory minimum’ to a more comprehensive station
Step 1.4.1 - Construction of
suitable buildings
Step 1.4.2 - Construction of
a run-round loop
Step 1.4.3 – Construction of
a second platform
Step 1.4.4 - Erection of a
footbridge at Blaenavon (High Level) station.
This is a relatively long
term step, and as yet no serious attempts have been made to seek funding. However circumstances have permitted a start
to be made on Step 1.4.1 (Buildings), and it is planned that some funds may be
diverted in order to progress the job a little further. We have also been able to dig out and expose
the remains of platform 2 (Step 1.4.3), though no construction work has started
yet. We have even identified not one,
but two suitable footbridges (Step 1.4.4), so that once Step 1.5 (Big Pit
branch) is finished, we may be able to concentrate on Step 1.4.
Step 1.5 – Visitor Centre and branch line to Big Pit
This step was the most
physically ill-defined step within Phase 1, and grew from the need to
accommodate the possibility of making a substantial bid to HLF. However interest from the HOV programme, has focussed
attention on this branch line to Big Pit element, funding is to hand, and
physical work on this project has started, though the main work is only just
beginning. The plan envisages running a
very short ‘Colliers Train’ over the 600m or so line. This would consist of open wagons in good
weather, or closed box vans otherwise.
Interchange with ‘main line trains’ would be at Furnace Sidings
station. The notion behind this plan is
to provide the opportunity, insofar as is possible, for visitors to experience
riding on miner’s works trains – a unique selling point amongst heritage
railways. At present the Visitor Centre
requires further progress on the HLF application.
Step
1.6 – Extension to Top Shed
The area is now clear for the Top Shed to be extended
backwards by about 100ft – nearly twice its original length. Funding for this work has come largely from
members. Steelwork and some roofing
panels have been installed for about half of the extension, and with the back
of Step 1.2 broken, labour can be directed to progressing this work.
Step
1.7 – Fencing around Down Exchange Sidings
This was an attempt to bring back into use four
sidings backing onto but nevertheless outside our security fence. By adding one long side and two short ends,
and removing the fence that separated the sidings from the main yard, we were
able to effectively enlarge the yard. It
has become very useful for storing operational stock and stock undergoing
restoration.